Performance Evaluation of Construction Project in Erbil City by adopting Site Layout planning

Authors

  • Haval M. Salih 1Department of Civil Engineering, Tishik International University, Erbil, Iraq, 2Four Bridges Company, World Trade Center, OF 602, Erbil, Iraq https://orcid.org/0000-0001-6201-828X
  • Ahmet Oztas Department of Civil Engineering, Tishik International University, Erbil, Kurdistan Region,Iraq
  • Omed Dewary Department of Civil Engineering, Tishik International University, Erbil, Kurdistan Region,Iraq
  • Ayman A. Ahmed Department of Civil Engineering, Tishik International University, Erbil, Kurdistan Region,Iraq

DOI:

https://doi.org/10.25156/ptj.v9n2y2019.pp76-79

Keywords:

Construction facilities, Performance, Safety, Site layout planning, System

Abstract

In general, construction site management is planning, organizing, leading, directing, monitoring, and controlling overall construction activities, during the implementation phase, one of the key elements of construction site management is site layout planning, which is identifying, sizing, and placing temporary facilities within construction boundaries. It has got enormous influence on project parameters. The main aim of this study is to investigate Erbil’s project’s site layout performance. The study was carried out in Erbil, 16 projects have selected for assessment. From the result, it was found that these projects suffer from poor site layout planning, as there was a poor plan for construction facilities, the location of these facilities was wrong, almost, all projects have neglected safety-related issues and much more factors which have been discussed in the analysis section. As a solution, the researcher believes that the current site layout design of projects need immediate improvement, planning should be considered as priority for every single temporary facility during construction; safety basic should be implemented, including wearing PPE; labor accommodation should be improved; sanitation of the workforce should be good; and many other site layout elements should be developed.

Downloads

Download data is not yet available.

References

Andayesh, A. and F. Sadeghpour. 2013. Dynamic site layout planning through minimization of total potential energy. Autom. Constr. 31: 92-102.

CFPA, Guidline. 2012. Fire Prevention on Construction Site. Copenhagen: CFPA Europe.

CINTAS. n.d. The Importance of Fire Prevention Plan at Your Facility. Available from: http://www.cintas.com/fire- rotection-services/ articles/the-importance-of-a-fire-prevention-plan-at-your-facility. [Last accessed on 2018 Jul].

Cleland, D. I. 2007. Project Management: Strategic Design and Implementation. 5th ed. McGraw Hill Global Education Holdings, New York.

Cleland, D. R. 2006. Global Project Management Handbook: Planning, Organizing, and Controlling International Projects. 2nd ed. McGrew Hill Global Education Holding, New York.

Elbeltagi, E. 2012. Construction Site Layout Planning. Available from: https://pdfs.semanticscholar.org/2e81/544f32d8c0849fcb6dff69cd2a72ba9ca633.pdf?_ ga= 2.244898053.1491129312.158

Elbeltagi, E., T. Hegazy and A. Eldosouky. 2004. Dynamic layout of construction temporary facilities considering safety. J. Constr. Eng. Manage. 130(4): 534-541. 1691418-188258 4169 .1581691418. [Last accessed on 2018 Jul].

Elbeltagi, E., T. Hegazy, A. Hosny and A. Eldosouky. 2001. Scheduledependent evolution of site layout planning. Constr. Manage. Econ. 19(7): 689-697.

Halpin, D. W. and B. A. Senior. n.d. Construction Management. 4th ed. John Wiley and Sons, Inc., Hoboken,

New Jersey.

Haytham, M. S., A. Mohammed and E. Moheeb. 2008. Optimum construction site layout considering safety and environmental aspectspp. J. Constr. Eng. Manage. 134: 536-544.

Hegazy, T. and E. Elbeltagi. 1999. Evosite: Evolution-based model for site layout planning. Am. Soc. Civ. Eng.

(3): 198.

Karray, F., E. T. Zaneldin, T. Hegazy, A. Shabeeb and E. Elbeltagi. 2000. Computational Intelligence Tools for Solving the Facilities Layout Planning Problem in American Control Conference, Chicago.

Kynyn, K. 2011. Construction Site Management Accessibility Ezinearticles. Available from: https://www.ezinearticles.com/?construction-site-management---accessibility &id=6102268. [Last accessed on 2018 Jul].

Lambeck, R. and J. Eschemuller. 2009. Urban Construction Project Management. McGraw-Hill Global Education Holdings, New York.

LeValley, M. 2016. Construction Fencing: Temporary Fence Rules in New Bedford? Valtran.

Levy, S. 2007. Project Management in Construction. 5th ed. McGraw Hill Professiona, New York.

Lin, J. J., C. E. Yang, W. H. Hung and S. C. Kang. 2113. Accessibility evaluation system for site layout planning a tractor trailer example. Vis. Eng. 12(1): 12.

Muiruri, G. and C. Mulinge. 2014. Health and Safety Management on Construction Projects Sites in Kenya a Case Study of Construction Projects in Nairobi County. FIG Congress 2014. Kuala Lampur. Available from: https://www.fig.net/resources/proceedings/fig_proceedings/fig2014/papers/ts07k/TS07K_

muiruri_mulinge_6847.pdf. [Last accessed on 2018 Jul].

Mulchay, R. n.d. PMP Exam Prep. 8th ed. RMC Applications, Inc., Rajkot.

Oberlender, G. 2014. Project Management for Engineering and Construction. 3rd ed. McGraw-Hill Global Education Holdings, New York.

OSHA. 2011. from United State, Department of labour, Occupational Safety and Health Administration. Available from: https://www.osha.gov/pls/oshaweb/owadisp.show_document?p_table=STANDARDS&p_id=9790. [Last accessed on 2018 Jul].

Patil, A. D. and D. Joshi. 2013. A review paper on construction site layout. J. Innov. Eng. Technol. 3: 233-236.

Shetty, S. V. and A. R. Deshmikh. 2013. A review paper on identification of crucial site layout planning factors in construction. Int. J. Sci. Res. 6(14).

Tommelein, I., R. Levitt and B. Hayeth-Roth. 1992. Sight plan experiments: Alternative strategies for site layout design. J. Comput. Civ. Eng. 5(1): 42-65.

Tommelein, I., R. Levitt and B. Hayeth-Roth. 1992. Sight plan model for site layout. J. Constr. Eng. Manage.

(4): 749-766.

Zouein, P. and I. Tommelein. 1999. Dynamic layout planning using a hybrid incremental solution method. J. Constr. Eng. Manage. 125(6): 400-408.

Published

2019-12-01

How to Cite

Salih, H. M., Oztas, A. ., Dewary, O., & Ahmed, A. A. (2019). Performance Evaluation of Construction Project in Erbil City by adopting Site Layout planning. Polytechnic Journal, 9(2), 76-79. https://doi.org/10.25156/ptj.v9n2y2019.pp76-79

Issue

Section

Research Articles